Road and Rail lines in the Border Regions of Himalayas

Inherently rail lines are more reliable and efficient than roads. As we go up in the Himalayas it is difficult to get speeds above 20 kmph even in fair weather.

In monsoon roads are frequently ..

theprint.in/defence/modi-g…
..blocked by landslides.

But with its utterly flawed alignments, that too on Broad Gauge, Rly Board has messed up all the ongoing seven projects.

India should go for a trans-Himalayan rail network on MG from north-west to northeast.

China is..

.. systematically building a rail network on its side of Himalayas which along with roads will serve a vast area from Sichuan to the western end of Tibet.

I am working on such a plan of lines in Himalayas in India.

#Himalayas
#Lines_in_Himalayas

Read 9 tweets
Kerala Silverline: My take on Panel Discussion

People of Kerala get a bigger dose of disinformation as Suboth Jain bats for KRDCL.

There is the added dose of seize mentality: Rly Bd/Central Govt is not interested in raising speed on the existing lines & building new lines..
..for higher speed of trains, so go for loan from Jica even if it means building a standalone line on SG which will be subsidized for ever by the taxpayer for travel by the affluent.

So govt subsidy for the affluent by the taxpayer.

I will post a detailed analysis tomorrow.
..To R. V. G. Menon:

Sir, you came out swinging! Suboth Jain couldn't give straight answer to even question. For example, your question about existing trains not being able to run on the Standard Gauge Silverline.

#K_Rail #Kerala_Silverline
#AlignmentSurveys #GroundSurveys
Read 4 tweets
K-Rail and Railway Board's history of approving projects without proper ground surveys & feasibility studies

With Railway Board still dragging its feet about rescinding the In-principle Approval for the K-Rail plan, it is necessary to ask why Railway Board refuses to learn..
.. lessons from its fiasco in Himalayas where since 1997, Rly Bd approved alignments for as many as eight new line projects in the challenging landslide-prone terrain without any ground surveys, on just paper alignments.

My post in the link above contains a detailed account.... ImageImageImageImage
..The latest victims of this approach are the plan for the semi-highspeed line in Kerala & the strategically important Bilaspur-Manali-Leh line.

#KeralaSemiHighspeedProject #Kashmir_rail_link #Chenab_Rail_Bridge #Ruling_Gradient #AlignmentSurveys #GeologicalSurvey #railwayboard ImageImageImage
Read 4 tweets
K-RAIL: WHY HAS RAILWAY BOARD NOT TAKEN ANY ACTION AGAINST MD/KRDCL FOR SUBMITTING FEASIBILITY REPORT BASED ON GOOGLE EARTH AND NO SURVEYS OF GROUND CONDITIONS & RIDERDHIP & DECIDING TO ADOPT STANDARD GAUGE?

Will Rly Board go on giving in-principle..1/3

english.mathrubhumi.com/news/kerala/e-…
..approvals in future also to projects involving this magnitude of public expenditure based on such fraudulent, concocted & cooked up feasibility reports?
.. 2/3

#Kerala_Silverline_Project
#KeralaSemiHighspeedProject
#AlignmentSurveys #IR_EngineeringCode
Read 7 tweets

Related hashtags

Did Thread Reader help you today?

Support us! We are indie developers!


This site is made by just two indie developers on a laptop doing marketing, support and development! Read more about the story.

Become a Premium Member ($3.00/month or $30.00/year) and get exclusive features!

Become Premium

Too expensive? Make a small donation by buying us coffee ($5) or help with server cost ($10)

Donate via Paypal Become our Patreon

Thank you for your support!